Project Overview

The Marina Park project encompasses a 10.5-acre site and involves new construction of a public park; a 24,000-square-foot Community and Sailing Center building; a 23-slip marina; a reconstructed 19th Street restroom building; a freestanding playground lighthouse feature; themed playground; outdoor fitness circuit; parking lots; and frontage street improvements. The buildings in this project are designed to meet LEED Silver rating requirements.

The park will also be home to the new 6,100-square-foot Girl Scouts Leadership Center, which is being funded entirely by the Girl Scouts of Orange County.

PROJECT UPDATES:

Marina Park Project: Package 1 - Demolition and Tree Relocation was awarded to Unlimited Environmental, Inc. on 10/22/2013.

On 03/25/2014, Council accepted the completed work and authorized the City Clerk to file a Notice of Completion for Package 1.

Marina Park Project: Package 2 - Marina Basin Construction including Dredging, Bulkheads, Grading and Soil Remediation was awarded to Dutra Construction Company on 12/10/2013.

Construction for Package 2 is currently underway, with stone columns and sheet pile installations having recently been installed.

Marina Park Project: Package 3 - Building & Site Development

A Notice Inviting Pre-Qualification Submittals was published in November 2013 in for General Contractor Pre-Qualification.

The following building General Contractors were pre-qualified to submit a bid for Marina Park Package 3:

Austin Commercial
Bernards
Erickson-Hall Construction
KPRS Construction Services, Inc.
Perera Construction & Design, Inc.
ProWest Constructors
Stronghold Engineering
Swinerton Builders
TB Pennick
W.E. O'Neil Construction Company
Kemp Bros. Construction
Malcraft, Inc
Morillo Construction, Inc.
P.H. Hagopian Contractor, Inc.

Bid Schedule:

  • Mandatory Pre-Bid Meeting -  03/13/2014, 9:00AM - 1770 W. Balboa Boulevard (18th Street Parking Lot)
  • Final Day to Submit Substitutions - 03/18/2014, 5:00PM
  • Final Day to Submit Bidder Questions - 03/28/2014, 5:00PM
  • Bid Opening - 04/15/2014, 2:00PM
  • Council Award - To Be Detemined pending final review of submitted Bids
 

 

Project Summary Schedule
  Date Status
Start Marina Park Construction December 2013 In Progress
Marina Park Anticipated Finish Spring 2016

Updated:  April 17, 2014

Perspectives                                              
Marina Park Aerial View

Proposed Aerial View                     

Photo 1

Proposed Site Plan

Photo 2

Proposed Facility-Street View

Photo 3

Proposed Facility-Bay View

 

Fact Sheet

Newsletters 

Reports

Photos

Please click here to view photos of the ground breaking ceremony which took place on February 11, 2014.

Marina Park Information Hotline

Please call 949-644-3366.

For more information. If you would like to be added to the “Interested Parties” e-mail list so that you’re notified of Marina Park information, please click here and create an account.

If you are having trouble creating an account but would like to be added to the list please contact Kelsey Kenz at 949-644-3330.

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Download Acrobat Reader Download Flash Player Download QuickTime Download Windows Media Player Download Microsoft Silverlight Download Word Viewer Download Excel Viewer Download PowerPoint Viewer
Last updated: 4/17/2014 12:04:09 PM