Marina Park Site Plan-Page Banner

1600 West Balboa Boulevard, Newport Beach, CA 92663

Project Overview

The Marina Park project encompasses a 10.5-acre site and involves new construction of a public park; a 24,000-square-foot Community and Sailing Center building; a 23-slip marina; a reconstructed 19th Street restroom building; a freestanding playground lighthouse feature; themed playground; outdoor fitness circuit; parking lots; and frontage street improvements. The buildings in this project are designed to meet LEED Silver rating requirements.

The park will also be home to the new 6,100-square-foot Girl Scouts Leadership Center, which is being funded entirely by the Girl Scouts of Orange County.

Construction Updates:

 Marina Park Project: Package 1 - Demolition and Tree Relocation was awarded to Unlimited Environmental, Inc. on 10/22/2013.  On 03/25/2014, Council accepted the completed work and authorized the City Clerk to file a Notice of Completion for Package 1.

Marina Park Project: Package 2 - Marina Basin Construction including Dredging, Bulkheads, Grading and Soil Remediation was awarded to Dutra Construction Company on 12/10/2013.  Construction for Package 2 is currently underway, with stone columns, sheet pile installations, tiebacks, and beach replenishment completed.  Dutra is currently focused on the balance of dredging work with an anticipated completion date of late September 2014.

Marina Park Project: Package 3 - Building & Site Development  was awarded to KPRS Construction Services, Inc on 05/13/2014.  Focus has been placed on site demolition, shop drawings, and utility construction.  Sidewalk and road closures along 18th Street, 15th Street, West Balboa Blvd., and West Bay Avenue should be expected after the Labor Day weekend.  Please subscribe to the Marina Park Interested Parties list by clicking here for the latest closure information.

Marina Park Project: Package 4 - Docks  The package 4 plans are currently being finalized.  The City is anticipating to advertise for construction bids in Fall 2014.

 

Project Summary Schedule
  Date Status
Start Marina Park Construction December 2013 In Progress
Marina Park Anticipated Finish Spring 2016

Updated:  August 20, 2014

Perspectives                                              
Marina Park Aerial View

Proposed Aerial View                     

Photo 1

Proposed Site Plan

Photo 2

Proposed Facility-Street View

Photo 3

Proposed Facility-Bay View

 

Fact Sheet

Newsletters 

Reports

Photos

Please click here to view photos of the ground breaking ceremony which took place on February 11, 2014.

Marina Park Information Hotline

Please call 949-644-3366.

For more information. If you would like to be added to the “Interested Parties” e-mail list so that you’re notified of Marina Park information, please click here and create an account.

If you are having trouble creating an account but would like to be added to the list please contact Kelsey Kenz at 949-644-3330.

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Download Acrobat Reader Download Flash Player Download QuickTime Download Windows Media Player Download Microsoft Silverlight Download Word Viewer Download Excel Viewer Download PowerPoint Viewer
Last updated: 8/21/2014 8:01:59 AM