The purposes of this Assessment District is to provide financing to underground power, telephone and cable facilities in the area generally bounded by G Street / East Balboa Boulevard / Channel Road / Ocean Boulevard. The proposed underground utility improvements will provide conversion to an upgraded utility system and will enhance neighborhood aesthetics, safety and reliability.

Associated Documents

Summary of the Assessment Engineer's confirmed costs for Project
(A more detailed table can be located in the Engineer's Report)

Engineers Estimate

Constructions Costs
    Electrical Costs (Southern California Edison)
        Electrical Construction Costs

                                3,053,100

        Construction Contingency (~10%)

305,310

        Edison Design Engineering

135,800

                                        Total Electrical Costs

$ 3,494,210

    Telephone Costs (AT&T)
        Telephone Construction Cost

992,998

        Construction Contingency (~10%)

99,300

        AT&T Design Engineering

102,000

                                        Total Telephone Costs

$ 1,194,298

        
        Street / Alley Rehabilitation

1,000,000

            Construction Contingency (~7.5%)

75,000

                                        Total Rehabilitation

$ 1,075,000

        Utility Contribution for Overhead

(678,621)

                                        Total Construction Costs

$ 5,084,887

                                              Less deduct from contingency

(19,744)

                               Modified Total Construction Costs

$ 5,065,143

Incidental Expenses
    Assessment Engineering

64,000

    Contract Inspection

75,000

    Disclosure Counsel

20,000

    City Administration

100,000

    Financial Advisor

15,000

    Filing Fees

5,000

    Bond Counsel

25,000

    Paying Agent

3,000

    Dissemination Agent

3,000

    Financial Printing, Registration and Servicing

10,000

    Incidental Contingencies

28,113

                                        Total Incidental Costs

$ 348,113

                                              Less deduct from contingency

(1,352)

                               Modified Total Construction Costs

$ 346,761

Total Incidentals & Construction Costs

$ 5,411,904

Financing Costs

 

    Uderwriter's Discount

77,759

    Bond Reserve/ Credit Enhancement

373,396

    Funded Interest at 12 months at 5.75%

357,693

                                        Total Financial Costs

$ 808,848

Total Amount to Assessment 

$ 6,220,752

*Time Warner Cable is required to pay for undergrounding through the Franchise Agreement with the City

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Download Acrobat Reader Download Flash Player Download QuickTime Download Windows Media Player Download Microsoft Silverlight Download Word Viewer Download Excel Viewer Download PowerPoint Viewer
Last updated: 3/28/2011 12:24:51 PM