Show/Hide

Corona del Mar Library & Fire Station Project

Print

Option 3 FribraryThe existing Corona Del Mar Fire Station No. 5 and the Corona Del Mar Branch Library went into service separately approximately sixty years ago. Both of these buildings have exceeded their intended service life and need to be replaced.

The Project Team (City staff and WLC Architects (WLC)) met with the Community numerous times over the past several months to fine-tune the numerous conceptual designs. Upon selecting a final design by the Library Board of Trustees and obtaining approval from the City Council earlier this year, WLC has been busy preparing the final construction plans and contract documents.

The Fire Station Crew/Operations relocation to the City parking lot at the northwest corner of 5th Avenue and Marguerite Avenue (across the street from the OASIS Community Center) and the start of substantial construction will likely begin in early 2017, for a 12-14 months construction period.

 

DSC05220

 

DSC05205 

The City contracted with WLC Architects (WLC) on March 24, 2015 for design and construction document preparation for the new Corona Del Mar Library and Fire Station.  The Design Team has met with the building users and implemented the received comments and ideas into four floor plans:

Option A

Option B

Option C

Option D1

Option D2

Option D3

*NEW Option D4* - Recommended by the Board of Library Trustees on October 19, 2015 and November 16, 2015. Approved by City Council on November 24, 2015.

 

ARCHITECTURAL RENDERINGS

Rendering 1

Rendering 2

Rendering 3 - Recommended by the Board of Library Trustees on October 19, 2015 and November 16, 2015. Approved by City Council on November 24, 2015.

 

WLC Architects, Library and Public Works staff (the Design Team) are continuing to work on preliminary layouts and have generated several different layouts for consideration.  The D-series options are receiving the most favorable responses from the Board and the community.  However, a preferred layout has not been approved at this time.  WLC is also developing exterior rendering concepts, with an emphasis of incorporating a balanced neighborhood architectural theme into the building façade.  Final City Council approval of the preliminary layout and renderings is expected in fall of 2015.

Community outreach and public review to date:

April 20, 2015 - Library Board of Trustees Meeting and presentation

May 18, 2015 - Library Board of Trustees Meeting  and presentation

June 15, 2015 - Library Board of Trustees Meeting and presentation at the CdM Branch

July 20, 2015 - Library Board of Trustees Meeting and presentation 

September 14, 2015 Community Meeting at Sherman Gardens

September 21, 2015 - Library Board of Trustees Meeting and presentation of options and renderings

October 19, 2015 - Library Board of Trustees Meeting

November 16, 2015 - Library Board of Trustees Meeting

Upcoming outreach and public review

November 24, 2015 - City Council approval of the preliminary design, layout and rendering.  

Design Schedule

Fall 2015 to Winter 2016 

Construction Schedule

Relocation and construction is expected to begin early 2017. Construction will require 12 to 14 months to complete.  

For questions, comments and suggestions, please email us at pwinfo@newportbeachca.gov

 

 

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer