Hazard Reduction Inspection Schedule
Hazard Reduction Biennial Inspections
The Hazard Reduction Inspection are conducted biennially by an outside contractor. The contractor maps out vegetation on properties and provides maps to the homeowners and fire department for hazard reduction.
Schedule
Even years = Buck Gully (Lower, middle, and upper)
Odd years = Big Canyon, Morning Canyon, and Newport Coast
Approx. June 7
The contractor begins first inspection which takes approx. 3-4 days
Approx. August 1
The contractor begins second inspection of parcels that were previously found non-compliant during initial inspection.